Tuesday 30 October 2012

Lockup and beyond

Since I last posted, we have officially met lockup and moved into fixing stage. I've spoken to our S/S yesterday who confirmed that the renderer is scheduled for this week and the carpenter is booked in next week to commence on the internal doors. Next week will also see the architraves completed, with the painter scheduled to start on 7th November!

Here are some updated pics of the interior of the house.

P.S - thanks to those that have left comments, I hope someone else building is able to get something out of the blog
 
Entry

Master Bedroom


Ensuite

 
Family 

 
Kitchen

 
Looking into Rumpus 
 
Main Bathroom

Wednesday 17 October 2012

Approaching lockup

We are fast approaching lock up (which is scheduled for tomorrow) so thought it might be a good time to post some recent pics. Since these were taken we've had electrical rough ins, heating/cooling rough ins and were waiting on confirmation that the rough in for the ducted vacuum had happened.

Also over today and end of tomorrow there are a few minor things to be fixed up as per our independent inspection. So far, we are ahead of schedule and hope it continues like this.

Plastering is due to start next Tuesday 23rd October which we've been told will take about a week. I will be able to update with more pics after our walk through early next week





 



Entry


Master Bedroom complete with electricity box




View from Master Bedroom - WIR on left and ensuite on right
 
 
Lounge


Kitchen with hallway and bathroom in background
 
Rumpus in background with feature niche wall

Bricks have commenced (Cat 4 - Boral Mocha)



 

 



Friday 5 October 2012